It's back to the trenches for contractor Tapani today as the company works toward a November deadline to complete the latest phase of the Astoria CSO separation project downtown. Here is a rundown on work expected to take place the rest of this holiday shortened week.

On 8th St, the new waterline that has been installed from Commercial to Franklin is expected to be put into service. Also this week, Century Link will be working on removing/relocating a telephone vault at the intersection of 8th St and Exchange to allow installation of the new sewer and storm pipe.

Tapani is expected to finish the final stretch of storm pipe installation from Jerome to Kensington on 10th St this week. Concrete installation of curbs and intersection corner ramps is expected to be done over the next couple weeks on 10th St.

Preparations for the pipe bursting and slip-lining on 9th Street from Marine Drive north to the Columbia River have begun with the primary effort scheduled for this week. On Tuesday or Wednesday, an entry pit will be dug on the south side of Marine Drive on 9th Street. During this construction, it will be necessary to close one lane of traffic on Marine Drive at 9th Street and close 9th Street entirely from Commercial St to Duane St, which is expected to take 4 to 7 days. The actual pipe bursting operation is expected to take 4-6 hours and is currently scheduled for Thursday, May 30th. During the pipe bursting process, Commercial Street will be reduced to one lane of traffic from 7th Street to 10th Street.

Connect With KAST

        

KAST 1370 AM

E-Newsletter & Breaking News Alerts

Brought to you by: